Reshoring and Backpropping Explained: How Slabs Are Supported After the Forms Come Off
What reshores, backshores and backpropping are, how construction loads pass down through floors, and what gets checked before props or forms come out.
Level 9 went in on Tuesday. By Thursday morning the deck forms under level 8 are wanted on level 10, the crane is booked, and a foreman radios the one question that matters. What's holding the new load up?
Reshoring and backpropping are the answer, or part of it. After a slab's forms come off, props go back under it so a young floor doesn't have to carry the wet floor above by itself. The Vietnam Plywood Atlas is published by Vinawood with a transparent mill affiliation, and this page sits next to the mill's commercial notes on formwork removal time. We're looking at the load path after the plywood deck has gone. Panel grades stay out of it.
Why a three-day-old slab ends up carrying a floor
Tall flat-slab buildings are built on a beat. Pour, strip, lift the kit, pour again. Nobody can afford a separate set of deck forms for every level, so the contractor strips as early as the engineer allows and sends the same sheets and props up the building. Fast. Efficient. And hard on whatever sits underneath.
Here is the catch. Pour level 9 and its wet weight, plus the forms, plus the crew and the rebar stacked on it, all go down through the shores into level 8. Level 8 may be a few days old. Its design strength is a 28-day number, and it hasn't got there. The designer never promised that a floor that young could take a fresh slab alone.
The load keeps going. Shores under 9 stand on 8, shores under 8 stand on 7, and the chain runs to the ground. How much each floor takes depends on how stiff the floors are next to the props between them. Near the top, the slabs are the youngest and the most loaded. Bad overlap. Planners lose sleep over exactly this.
Shores, preshores, reshores, backshores
Shores first. They hold the forms and the wet concrete until the slab can stand, and they belong to the temporary works described in the falsework guide and the soffit systems in slab formwork explained. They go in before the pour and come out afterwards. Nobody calls a shore a reshore.
Reshores go in afterwards. ACI Committee 347 uses the word for shores placed snugly under a slab once the original forms and shores have been taken out of a large area. The slab has been let go. It deflects, picks up its own weight and whatever construction load already sits above it, and only then do the reshores start sharing what comes next. A second line of support that wakes up when the first one leaves.
Backshores are the gentler cousin. In the same ACI vocabulary, a backshore is placed under a slab after the originals have been removed from a small area, and the slab is never allowed to deflect under its own weight. It stays held. The crew strips around the prop, not past it.
Preshores are a different move again. They go in before stripping begins and stay put while the forms around them are removed, so the slab never loses support at all. Add the site word, backpropping, and you have a vocabulary problem. Backpropping turns up in tenders and morning briefings as a loose name for any prop returned under a stripped slab. It is rarely defined where it's used. If a drawing says only backprop, ask which of the four the engineer actually means.
How construction loads move down the building
Picture the stack. The top slab is poured and its weight lands on props, the props push into the slab below, and that slab bends a little. As it bends, it passes some of the load on through the props under it to the next slab down. The more floors that join in, the less any single floor has to take.
ACI 347.2R models that sharing with a simplified method, and the guide gives whole chapters to load distribution and to early-age slab strength. The answer depends on shoring layout, slab thickness, the age of each slab at each step, and whether the building is post-tensioned, which moves load around in its own way. We don't print any of those values here. They belong to the engineer's calculation for one specific building.
Two practical points need no calculator. A prop cranked tight under a stiff slab can draw load the designer never planned for. And a prop with a gap at the top carries nothing until the slab above has sagged down to touch it. "Snug" is a technical word on a formwork drawing. People who write it mean it.
What gets checked before anyone strips
Days on the calendar are a rough proxy. A cold week turns a three-day assumption into a bad one. The crew needs the concrete's real strength, usually from cylinders or maturity monitoring, set against the strength the engineer of record asked for before that slab takes the next load.
OSHA lands in the same place in 29 CFR 1926.703. Forms and shores don't come out until the employer determines that the concrete has gained enough strength for its own weight and the loads on it, and that call rests on conditions in the plans and specifications or on standard compressive-strength tests. Reshoring gets the same treatment. Supports that were put back aren't pulled on a hunch either.
The striking-time guide walks through the strength gate for forms, and the mill's note on concrete pressure on formwork covers the earlier question of what fresh concrete does to the face. Reshoring comes third. Face first, strike second, support after.
Sequence is on the list too. ACI 347.2R says failures from improper reshoring, premature removal of supports and weak lateral bracing have turned up throughout the history of concrete building. Pull the wrong bay first, or lift a row of props before the next row is tightened, and a slab that checked out on paper takes a load nobody ran. Order counts as much as strength does.
Who owns the decision
It's engineering work, and the owners have titles. The formwork designer lays out shoring and reshoring. The engineer of record sets the strength each stage needs. The contractor runs the sequence and keeps the evidence. A page like this can't stand in for any of them and doesn't try.
What it can do is let a buyer, specifier or importer read the drawing. A takeoff that lists plywood decking and says nothing about reshores hasn't been priced for the system the sheets will actually sit in. Faster stripping changes how many sets of deck forms a job needs. A slow reshoring plan can quietly add one. Those are scheduling effects. The plywood is still plywood.
Where the sheet comes in: a deck face that is stripped on day three goes straight back into service on the next level, so edges, overlay and release practice have to survive a short, repeated cycle. The concrete forming plywood guide covers face families, and the mill's piece on slab formwork plywood covers the buyer side. The props underneath belong to another trade and another drawing.
Terms at a glance
| Term | When it goes in | What it carries |
|---|---|---|
| Shores | Before the pour | Forms and wet concrete until the slab can stand |
| Preshores | Before stripping starts | Keep the slab supported while the forms come out |
| Reshores | After stripping a large area | Share load once the slab has taken its own weight |
| Backshores | After stripping a small area | Hold the slab without letting it deflect under its own weight |
| Backpropping | After stripping | Site name for props returned under a stripped slab; confirm which type |
Frequently asked
What is reshoring?
Reshoring is the practice of placing props snugly under a slab after its original forms and shores have been removed. The slab first takes its own weight, and the reshores then share the load from floors poured above. It lets contractors strip deck forms early and reuse them on the next level without overloading a young slab.
Is reshoring the same as shoring?
No. Shores go in before the pour and hold the forms and wet concrete until the slab can stand. Reshores go in after the original shores come out, and backshores stay snug under a slab without letting it deflect. Backpropping is a site word that can mean either, so the drawing should say which one applies.
How many floors of reshores are needed?
There is no single number. The count depends on the shoring layout, slab thickness, the age and strength of each slab, and whether the building is post-tensioned. ACI 347.2R describes the method for working it out, and the engineer of record or formwork designer applies it to the specific building.
Who decides when props can be removed?
The engineer of record and the formwork designer set the strength a slab needs before supports come out. The contractor checks the concrete against that requirement and records the evidence. OSHA 29 CFR 1926.703 says forms and shores are not removed until the concrete has gained enough strength for its own weight and the loads on it.
Related in the atlas
Continue reading
Same topic first, then what others on the atlas read most.

Formwork
Plywood Edge Sealing Explained: Why Formwork Panel Edges Fail First and How Sealing Works
Form panels usually fail at the edge before the face. Why end grain soaks up water, what factory edge sealing does and does not do, and why every site cut and tie hole needs resealing.

Formwork
Concrete Form Liners Explained: Textured Mould Faces for Architectural Concrete
What concrete form liners are, how they differ from fair-faced finish classes, which materials get reused, and why a flat plywood backing still matters behind the texture.

Formwork
Formply Explained: Australian F-Grade Formwork Plywood and AS 6669
Formply is the Australian and New Zealand trade name for concrete-formwork plywood ordered by F-stress grades such as F17 under AS 6669—not a waterproof claim and not APA MDO.